Mars Exploration Rover Project
LANDING SITE SELECTION SCHEDULE
- 9/00 Define Preliminary Engineering Constraints
- Preliminary Identification Potential Landing Sites-About Dozen (MER-A)
- Define Remote Sensing Criteria for Acceptable Sites
- 1/01 Open Landing Site Workshop - What Science Where?
- 3/01 Prioritized List of ~Half Dozen Sites - Target MOC Images
- 2 - 9/01 Detailed Evaluation of Sites-JPL, Project Scientists, MDAP Investigators
- 9/01 Reprioritization of Top Sites, 9/01 by Project
- With Input from Science Community, LSSC, and MEP
- Continue MOC Acquisition
- 4/02 Open Landing Site Workshop - Focus on Top 4 Sites
- Detailed Evaluation of Surface Characteristics and Science Potential
- Continued MOC, Start THEMIS Data Acquisition
- 4/02 - Landing Site Selection by Project
- With Input from Science Community, LSSC and MEP
- 5/02 - Headquarters Review & Approval
- 6/02 Delta LV Guidance Parameters for Landing Site
- Continued Evaluation of Selected Sites
- 6/03 Launch